Example Asbestos Removal Projects in Lakewood, California

The seven example jobs below are set in Lakewood, Cerritos and Hawaiian Gardens. Each one lists what was sampled, what came out, the work days and an estimated cost.

Ceiling and floor materials removed before a kitchen remodel permit is filed

Example project

Home
1950s tract house in Lakewood with a textured kitchen ceiling and vinyl over the original floor
Original request
Remodel the kitchen with new cabinets, a new floor and a smooth ceiling
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture, the vinyl, the mastic and the wall compound
Found
Asbestos in the ceiling texture and the mastic under the vinyl
Clear
The vinyl itself and the wall compound
Area
About 120 sq ft of ceiling and 130 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$4,200

Scope of work

Samples of each material, the district notice, the kitchen sealed with air filters running, the ceiling texture and the floor layers removed wet, bagging and the haul. The clearance air test, the permit and the remodel itself are separate.

Project overview

In this example, a family in Lakewood is remodeling the kitchen of a 1950s tract house. Building permit applications in the city now go straight to the City of Lakewood, and the asbestos notice goes to the district, a separate office with its own deadline.

The ceiling texture and the mastic test positive. The abatement crew clears both before the cabinet crew starts, and the permit work and the notice move along side by side.

The goal

The goal is a kitchen with the positive ceiling and floor materials gone, so the permitted work starts on clean surfaces.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every surface the remodel disturbs.
  2. Before work The contractor files the district notice online while the owners file the permit application with the city.
  3. Days one to three The kitchen is sealed, the ceiling texture comes down wet and the floor layers are lifted.
  4. Last An independent consultant tests the air, then the cabinet crew starts.

Planning right

  • Give the city the plans, and the district the notice, as two separate filings.
  • Keep the lab report with both sets of papers.
  • Order cabinets for after the air results.
  • Set up a coffee corner away from the kitchen.

Get a free quoteMore about renovation and demolition abatement

Positive materials removed from a 1970s house before it is demolished

Example project

Home
1970s two-bedroom house in Cerritos on a lot being cleared for a new home
Original request
Demolish the house and build new on the same lot
Testing
A whole-house survey by a Cal/OSHA-certified asbestos consultant, about 24 samples from ceilings, floors, walls and ducts
Found
Asbestos in the ceiling texture, the entry and kitchen floors and the wrap on the attic ducts
Clear
The wall compound and the window putty
Area
About 1,300 sq ft of ceiling and 380 sq ft of floor, plus the attic duct wrap
Timeline
Notice no later than 10 working days ahead, then six working days before the wrecking crew
Cost
$23,500

Scope of work

Removal of every positive material in the survey, the district notice, rooms sealed in turn, wet removal into labeled bags and the haul with its paperwork. The survey, the clearance air test, the demolition and the permits are separate.

Project overview

In this example, the owners of a 1970s house in Cerritos are replacing it with a new home. The city’s demolition application says the district must be notified of the demolition and of any asbestos removal, and the permit form carries an asbestos declaration.

The survey comes first and the district notice follows. The abatement crew removes the positive materials, and the wrecking crew begins after the air results.

The goal

The goal is a house with every positive material gone, so the wrecking crew starts clean.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every room and the attic ducts.
  2. Before work The contractor files the district notice online, and the owners complete the city permit form with its asbestos declaration.
  3. Days one to six Room by room the ceilings and floors come out wet, then the duct wrap in the attic.
  4. Last An independent consultant checks the air, and the wrecking crew starts.

Planning right

  • Order the survey when the new plans are first drawn.
  • Keep the district notice and the lab report with the city application.
  • Ask the wrecking crew to hold until the air results.
  • Leave room at the curb for the waste truck.

Get a free quoteMore about renovation and demolition abatement

Hallway and entry floor tile lifted ahead of new plank flooring

Example project

Home
1960s house in Hawaiian Gardens with vinyl tile in the hallway and entry
Original request
Lay new plank flooring from the entry through the hall
Testing
A Cal/OSHA-certified asbestos consultant samples the tile at three spots and the mastic beneath it
Found
Asbestos in the tile and the mastic
Area
About 85 sq ft of hall and entry floor
Timeline
Less than 100 square feet of renovation, so no district notice, then one working day
Cost
$1,800

Scope of work

Samples of the tile and mastic, the hall sealed with plastic, the tile lifted and the mastic removed wet to the subfloor, bagging, a cleanup and the haul. The clearance air test and the new flooring are separate.

Project overview

In this example, the owners of a 1960s house in Hawaiian Gardens are laying plank flooring from the entry through the hall. The old vinyl tile has to come up first so the planks sit flat.

The tile and its mastic test positive. The abatement crew lifts them in a day with the hall sealed, and the installer starts on a bare subfloor.

The goal

The goal is a bare hall and entry subfloor, so the plank flooring goes down on a clean base.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the tile in the hall and the entry.
  2. Results The tile and the mastic come back positive.
  3. Work day The hall is sealed, the tile is lifted by hand and the mastic comes off wet.
  4. Then An independent consultant tests the air and the installer begins.

Planning right

  • Move the shoe rack and the hall table out the day before.
  • Use the back door while the entry is sealed.
  • Order the planks for after the air results.
  • Keep the lab report with the flooring papers.

Get a free quoteMore about floor tile and mastic removal

Wrapped ducts removed when an air handler moves from a closet to the attic

Example project

Home
1950s tract house in Lakewood with the air handler in a hall closet and ducts above the ceiling
Original request
Move the air handler into the attic and give the closet back as storage
Testing
A Cal/OSHA-certified asbestos consultant samples the wrap on the plenum and the first branch ducts, and the closet wall tape
Found
Asbestos in the plenum wrap and the branch wrap
Clear
The closet wall tape
Area
Duct and plenum wrap in the attic
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,900

Scope of work

The closet and the attic hatch sealed, wet removal of the wrapped plenum and ducts into labeled bags, a cleanup and the haul. The survey, the clearance air test and the new air handler and ducts are separate.

Project overview

In this example, the owner of a 1950s tract house in Lakewood is moving the air handler from the hall closet up into the attic. The old plenum and the ducts around it come out, and that work counts as renovation under the district rule.

The plenum and branch wrap test positive. The abatement crew takes the old run out first, so the heating crew sets the new unit and ducts in a cleaned attic and closet.

The goal

The goal is a closet and attic free of the old wrapped duct, so the new air handler goes in clean.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the closet and the attic runs.
  2. Before work The abatement contractor files the district notice online and the heating crew holds its date.
  3. Days one and two The closet and hatch are sealed, and the plenum and ducts are wetted, cut apart and bagged.
  4. Last An independent consultant tests the air, then the heating crew installs the new unit.

Planning right

  • Empty the hall closet beforehand.
  • Ask the heating crew to wait for the air results.
  • Keep the lab report with the equipment papers.
  • Plan for a day or two without heating or cooling.

Get a free quoteMore about HVAC duct and pipe insulation removal

Acoustic ceiling texture removed before smooth drywall goes up

Example project

Home
1950s tract house in Lakewood with a sprayed acoustic texture on the front room ceiling
Original request
Hang new smooth drywall across the front room ceiling
Testing
A Cal/OSHA-certified asbestos consultant samples the acoustic texture at two spots
Found
Asbestos in the acoustic texture
Area
About 250 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,600

Scope of work

Two samples, the district notice, the front room sealed with air filters running, the texture soaked and scraped into bags, a HEPA clean and the haul. The clearance air test and the new drywall are separate.

Project overview

In this example, a Lakewood owner is replacing the front room ceiling of a 1950s house with new smooth drywall. The existing ceiling has a sprayed acoustic texture, and the drywall crew would be cutting and fastening through it.

Both samples test positive. The abatement crew takes the texture off first, and the drywall crew hangs the new sheets afterwards.

The goal

The goal is a ceiling with no positive texture, so the new drywall is hung and finished on a clean surface.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling at two spots.
  2. Before work The contractor files the district notice online and the owner clears the front room.
  3. Day one The room is sealed, and the texture is soaked and scraped into bags.
  4. Day two The ceiling is wiped down, the bags leave and an independent consultant tests the air.

Planning right

  • Take the lamps and the window coverings out of the room.
  • Book the drywall crew for after the air results.
  • Choose the new ceiling finish ahead of time.
  • Keep the lab report with the house papers.

Get a free quoteMore about popcorn ceiling removal

Wall compound removed from a bathroom vanity wall opened after a leak

Example project

Home
1950s house in Lakewood with a hall bathroom vanity on a wall that took water from a supply line leak
Original request
Open the wet wall, replace the vanity and redo the floor beside it
Testing
A Cal/OSHA-certified asbestos consultant samples the wall compound, the texture and the floor covering
Found
Asbestos in the wall compound and texture
Clear
The floor covering
Area
About 45 sq ft of wall
Timeline
Less than 100 square feet of renovation, so no district notice, then one working day
Cost
$1,600

Scope of work

Plastic around the bathroom and hall, the wall compound and texture removed wet from the vanity wall, bagging, a cleanup and the haul. The survey, the plumbing repair, the vanity and the new wall surface are separate.

Project overview

In this example, a supply line behind the vanity in a Lakewood hall bathroom has leaked, and the wall behind it has to be opened. The house is a 1950s tract house with the original wall finish.

The wall compound and texture test positive and the floor covering is clear. The abatement crew removes the vanity wall surface first, so the plumber works in an opened wall and not through the compound.

The goal

The goal is a vanity wall opened by the abatement crew, so the repair work goes ahead without disturbing positive compound.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wall and the floor.
  2. Results The wall is positive and the floor covering is clear.
  3. Work day The bathroom is sealed and the vanity wall is removed wet and bagged.
  4. Then The plumber repairs the supply line and the vanity is replaced.

Planning right

  • Photograph the damaged area for the repair file.
  • Empty the vanity and the cabinet above it.
  • Hold the new vanity order until the wall is open.
  • Keep the lab report with the repair invoice.

Get a free quoteMore about drywall, joint compound and plaster removal

Whole-house survey ordered by a buyer’s contractor for a house bought as-is

Example project

Home
1950s house in Lakewood bought as-is, with original ceilings, floors and walls throughout
Original request
Know what is in the house before the contractor bids a full remodel
Testing
A whole-house survey by a Cal/OSHA-certified asbestos consultant, about 18 samples from every room, the attic ducts and the garage
Found
Asbestos in the kitchen and bath floors, the hall ceiling texture and the attic duct wrap
Clear
The bedroom ceilings, the wall compound and the garage
Timeline
Samples, then lab results, then a written report
Estimated testing cost
$1,100

Scope of work

A visit by the consultant, about 18 samples, a lab result for each and a written report with the sample spots marked. Removing anything the survey finds is priced separately.

Project overview

In this example, a buyer in Lakewood has bought a 1950s house as-is and plans a full remodel. The contractor asks for a survey before pricing anything, because the bid has to include whatever has to come out first.

The report lists each material sampled, where and with what result. The contractor prices the abatement from it and sequences the remodel behind it.

The goal

The goal is one report that every bidder works from, so the remodel is priced with the abatement included.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every room, the attic and the garage.
  2. Results The lab reports each sample, with four materials positive and the rest clear.
  3. Next The contractor prices the removal of the positive materials from the report.
  4. Then The remodel schedule is set around the notice and the abatement days.

Planning right

  • Order the survey before the remodel bids, not after.
  • Give every bidder a copy of the report.
  • Ask the consultant to number the sample spots on a sketch.
  • Please do not take samples yourself.

Get a free quoteMore about asbestos testing and surveys

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (562) 303-5293

Call (562) 303-5293